Petition of the CERC (Connectivity and General Network Access to the Inter-State Transmission System) Regulations, 2022 – EQ

Petition of the CERC (Connectivity and General Network Access to the Inter-State Transmission System) Regulations, 2022 – EQ

0
0

Summary:

## ⚖️ **Petition Summary**

* **Petition No.**: 657/MP/2025
* **Filed By**: JSW Renew Energy Five Limited (JREFL)
* **Respondents**: Central Transmission Utility of India Ltd. (CTUIL) and others
* **Date of Hearing**: 17 July 2025
* **Forum**: CERC, New Delhi

## 📌 **Legal Basis**

* **Filed under**:

* Section **79(1)(c)** and **79(1)(f)** of the Electricity Act, 2003
* Regulations **41** and **42** of the CERC (Connectivity and General Network Access to the ISTS) Regulations, 2022

## 👨‍⚖️ **Coram**

* **Shri Jishnu Barua**, Chairperson
* **Shri Ramesh Babu V.**, Member
* **Shri Harish Dudani**, Member
* **Shri Ravinder Singh Dhillon**, Member

## 👥 **Parties Present**

### For **Petitioner (JREFL)**:

* Shri Aman Anand (Advocate)
* Shri Aman Dixit (Advocate)
* Ms. Natasha Debroy (Advocate)
* Ms. Shristi Gupta (Advocate)

### For **Respondent (CTUIL)**:

* Shri Shubham Arya (Advocate)
* Ms. Reeha Singh (Advocate)
* Shri Harshvardhan Singh (Advocate)
* Shri Ranjeet Rajput (CTUIL)
* Shri Swapnil Verma (CTUIL)

## 🧾 **Commission’s Orders**

1. **CTUIL** sought **additional time** to file its reply.
2. **Commission granted**:

* **4 weeks** to CTUIL for filing its reply (with a copy to the Petitioner).
* **3 weeks** thereafter for **JREFL** (Petitioner) to file a rejoinder, if any.
3. **Next Hearing Scheduled**: **7 October 2025**

## 🖊️ **Signed by**

* **T.D. Pant**, Joint Chief (Law), CERC

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network