Summary: —- ### Background Statement: – Under GNA Regulations, Connectivity Applicants must achieve three key milestones: 1. **Submission of land documents** (50% of required land) 2. **Achieving Financial Closure (FC)** 3. **Achieving Commercial Operation Date (COD)** – Failure to meet timelines results in **revocation of Connectivity** and encashment of Bank Guarantees. – Many entities have […]
Summary: — ## 📄 Case Overview | Parameter | Details | |———–|———| | **Petition No.** | 149/MP/2026 along with IA No. 45/2026 | | **Petitioner** | ReNew Green Energy Solutions Private Limited (RGESPL) | | **Respondent** | Central Transmission Utility of India Limited (CTUIL) | | **Subject** | Relief against CTUIL regarding grant of connectivity […]
Summary: — ### Business Points 1. **Critical Relief for ARIPL:** The continuation of interim protection (granted by APTEL on March 12, 2026) is a significant positive for ARIPL. This protection likely prevents CTUIL from taking adverse action (e.g., canceling or reducing connectivity) while the petition is pending. ARIPL must ensure no breach of conditions tied […]
Summary: — ### Reliefs Sought by SUCRL (Main Petition & IAs) 1. Relax timeline for land document submission – allow **12 months from final grant** or **12 months from issuance of coordinates** (instead of 18 months from in‑principle grant). 2. Alternatively, permit land document submission **18‑24 months before start date (31.12.2029)**. 3. Transfer/reallocate connectivity to […]
Summary: —- **Key Parties:** – **Petitioner:** Indosol Solar Private Limited (ISPL), a solar power generation company. – **Respondent:** Central Transmission Utility of India Limited (CTUIL), the central transmission utility. **Procedural Status & Key Developments:** 1. **Compliance Filed:** The Petitioner’s counsel informed the Commission that ISPL has complied with previous directives. A compliance affidavit dated February […]