Summary: — ### Reliefs Sought by SUCRL (Main Petition & IAs) 1. Relax timeline for land document submission – allow **12 months from final grant** or **12 months from issuance of coordinates** (instead of 18 months from in‑principle grant). 2. Alternatively, permit land document submission **18‑24 months before start date (31.12.2029)**. 3. Transfer/reallocate connectivity to […]
Summary: —- **Key Parties:** – **Petitioner:** Indosol Solar Private Limited (ISPL), a solar power generation company. – **Respondent:** Central Transmission Utility of India Limited (CTUIL), the central transmission utility. **Procedural Status & Key Developments:** 1. **Compliance Filed:** The Petitioner’s counsel informed the Commission that ISPL has complied with previous directives. A compliance affidavit dated February […]
Summary: — ### **1. Executive Summary** In the hearing dated **15 January 2026**, the Central Electricity Regulatory Commission (CERC) considered Serentica Renewables India Private Limited’s (SRIPL) petition seeking retention and extension of its **400 MW connectivity** at the Solapur substation. The petition arises due to delays in commissioning its **500 MW Hybrid Renewable Energy Project**, […]
Summary: — ### **1. SUBJECT OF THE PETITION** * **Petitioner:** Datta Power Infra Private Limited (DPIPL) * **Respondent:** Central Transmission Utility of India Limited (CTUIL) * **Relief Sought:** Interim directions to **restrain CTUIL** from taking **coercive actions** against DPIPL, including: * Revocation of in-principle connectivity grant. * Encashment of connectivity bank guarantees. * **Legal Basis:** […]
Summary: — # **1. Background** The Central Electricity Regulatory Commission (CERC) considered multiple representations from Renewable Energy Developers (RE Developers) and industry associations regarding operational challenges arising from the newly introduced framework of *Solar Hour Access* and *Non-Solar Hour Access* under the Third Amendment to the GNA Regulations. The Commission examined issues raised and issued […]
Summary: — ### 🔹 **Subject Matter** Petition filed under **Section 79(1)(f)** of the *Electricity Act, 2003* read with **Regulation 42** of the *CERC (Connectivity and General Network Access to the ISTS) Regulations, 2022*, seeking a **limited modification** in the *in-principle grant of connectivity* issued by **CTUIL**. — ### 🔹 **Parties** * **Petitioner:** Halvad Renewables Private […]