Summary:

## **Case Summary – PGCIL Tariff Petitions (Odisha Phase-II & Barh Systems)**

**Forum:** Central Electricity Regulatory Commission (CERC), New Delhi
**Date of Hearing:** 26 August 2025
**Coram:**

* Shri Jishnu Barua, Chairperson
* Shri Ramesh Babu V., Member
* Shri Harish Dudani, Member
* Shri Ravinder Singh Dhillon, Member

### **1. Petitions Covered**

* **189/TT/2025** – True-up (2019–24) & tariff determination (2024–29) for transmission assets under *“POWERGRID work associated with common transmission system for Phase-II Generation Projects in Odisha”* (Eastern Region).
* **378/TT/2025** – True-up (2019–24) & tariff determination (2024–29) for transmission assets under *“Barh Transmission System”* (Northern, Eastern & Western Regions).

**Petitioner:** Power Grid Corporation of India Limited (PGCIL)
**Respondents:** BSPHCL & other regional beneficiaries.

### **2. Proceedings**

* **In Petition 189/TT/2025:**

* PGCIL submitted that, in view of Commission’s earlier order (94/TT/2024, dated 25.10.2024), re-conductoring works must be claimed as Additional Capitalisation under the original project.
* Therefore, they sought amendment to include re-conductoring of Asset-1(i) (LILO of both circuits of 400 kV D/c Rourkela–Raigarh 2nd line with 4 × 400 kV bays at Jharsuguda GIS).

* **In Petition 378/TT/2025:**

* PGCIL sought amendment to include Additional Capitalisation and corresponding de-capitalisation related to SCADA upgradation at Ballia & Bhiwadi HVDC stations.

### **3. Commission’s Directions**

1. Allowed amendment of both petitions (subject to just exceptions).
2. **PGCIL to file amended petitions within 2 weeks**, with advance copy to Respondents.
3. **Respondents to file replies within 2 weeks** of receipt; PGCIL may file rejoinder within 1 week thereafter.
4. Matters to be listed for **hearing on 21 October 2025**.

### **4. Outcome**

* **Type of Order:** Procedural (Record of Proceedings).
* **Effect:** Petitions admitted but required to be amended (189/TT – reconductoring; 378/TT – SCADA ACE & de-cap).
* **Status:** Adjourned; pending amended petitions and replies.

For more information please see below link: