Summary: — #### **1. Case Overview** * **Petition Number:** 771/AT/2025 * **Petitioner:** **NTPC Limited** * **Legal Basis:** Filed under **Section 63 of the Electricity Act, 2003**. This section deals with the adoption of tariff discovered through a transparent process of competitive bidding. * **Subject:** The petition seeks the **adoption of tariff** for **1200 MW Wind-Solar […]
Summary: — ### **1. Background** **NTPC Limited (NTPCL)** filed a petition before the **Central Electricity Regulatory Commission (CERC)** under **Section 63 of the Electricity Act, 2003** seeking **adoption of tariff** for **1200 MW Wind-Solar Hybrid Power Projects**, with a **Greenshoe Option** for an additional capacity of up to **600 MW**. The projects are connected to […]
Petition for Adoption of Tariff of 1.2 GW ISTS Grid connected Wind – Solar Hybrid Power projects on anywhere in India basis with ‘Green- Shoe Option” For more information please see below link:
Petition for Adoption of Tariff of 1.2 GW ISTS Grid connected Wind – Solar Hybrid Power projects with ‘Green-Shoe Option” under by Ministry of Power, Govt. of India For more information please see below link:
Petition for Adoption of tariff for 600 MW inter state Transmission System connected Wind Solar Hybrid Power Projects (SECI ISTS IX) For more information please see below link:
Petition for Adoption of Tariff discovered for procurement of power from the 1200 MW ISTS-Connected Wind- Solar Hybrid Power Projects For more information please see below link:
Petition for approval of the Guidelines issued by Central Government for procurement of power from Grid connected Renewable Energy Sources Hybrid Power Projects For more information please see below link:
Petition for Adoption of tariff for 600 MW inter-state Transmission System connected Wind-Solar Hybrid Power Projects (SECI ISTS IX) For more information please see below link: