Summary:
—
## ⚖️ **Document Overview**
* **Issuing Authority:** Central Electricity Regulatory Commission (CERC), New Delhi
* **Document Type:** *Record of Proceedings (RoP)*
* **Petition No.:** 684/AT/2025
* **Date of Hearing:** *18 September 2025*
* **Coram:**
* Shri Jishnu Barua – Chairperson
* Shri Ramesh Babu V. – Member
* Shri Harish Dudani – Member
* Shri Ravinder Singh Dhillon – Member
—
## 🏢 **Petitioner**
**SJVN Limited** (Satluj Jal Vidyut Nigam Limited) — a Government of India enterprise primarily engaged in hydropower and renewable energy development.
—
## ⚙️ **Nature of the Petition**
The petition was filed under **Section 63** of the *Electricity Act, 2003* seeking:
> **Adoption of Tariff** discovered through **Tariff-Based Competitive Bidding (TBCB)** for setting up **1200 MW Inter-State Transmission System (ISTS)-connected Wind-Solar Hybrid Power Projects (HYBRID-3)** in India.
This is in accordance with the:
* *Ministry of Power (MoP)* **“Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Wind-Solar Hybrid Projects”** dated *21 August 2023*, and
* Its subsequent **amendments**.
—
## ⚡ **Project Description**
* **Capacity:** 1200 MW (Hybrid – combination of Wind and Solar)
* **Connectivity:** Inter-State Transmission System (ISTS)
* **Bidding Scheme:** *Wind-Solar Hybrid Scheme (HYBRID-3)* under MoP competitive bidding framework.
* **Purpose:** Procurement of renewable power through national-level competitive auctions.
—
## 👥 **Respondents**
* **Adyant Enersol Private Limited & Others** — likely the successful project developers or associated entities from the competitive bidding process.
—
## 🧾 **Proceedings Summary**
1. **SJVN’s Submission:**
* The petition seeks **adoption of tariffs** discovered via transparent competitive bidding for the 1200 MW ISTS-connected Wind-Solar Hybrid Projects.
* Submitted that all procedures under the *2023 MoP Bidding Guidelines* were followed.
* Filed an **affidavit dated 8 September 2025** containing additional documentation, including the **Conformity Certificate** confirming compliance with bidding guidelines.
* Noted that **no objections** were received from any respondent.
2. **CERC’s Observation and Direction:**
* The Commission granted **liberty to SJVN** to file a **Note of Arguments within one week**.
* The case was **reserved for final order** following submission of the written note.
—
## 🧠 **Legal Context**
Under **Section 63 of the Electricity Act, 2003**, the CERC is empowered to **adopt tariffs** for power procurement that have been discovered through transparent competitive bidding processes conducted in line with government-issued guidelines.
This ensures:
* Competitive market-based pricing for renewable power.
* Transparent and fair procurement mechanisms.
* Encouragement of hybrid renewable projects (combining wind and solar generation for grid stability).
—