Summary:
—-
## Key Details at a Glance
| Parameter | Details |
|———–|———|
| **Project Name** | Dabhota-I Solar Power Project |
| **Solar Capacity** | 9 MW (AC) |
| **Battery Storage** | 3.15 MW / 6.3 MWh BESS |
| **Location** | Dabhota, Solan District, Himachal Pradesh |
| **Bidding Format** | Single-stage, two-envelope system with e-reverse auction |
| **Contract Type** | Turnkey EPC + O&M |
| **O&M Period** | 15 years |
| **Bid Submission Deadline** | May 5, 2026 (2:00 PM) |
| **Technical Bid Opening** | May 5, 2026 (3:00 PM) |
## Important Dates
| Activity | Date & Time |
|———-|————-|
| Bid Document Sale Start | April 2, 2026 (10:00 AM) |
| Site Visit | April 16, 2026 |
| Pre-bid Meeting | April 18, 2026 (11:00 AM) |
| Last Date to Download Documents | May 5, 2026 (1:00 PM) |
| Bid Submission Deadline | May 5, 2026 (2:00 PM) |
| Technical Bid Opening | May 5, 2026 (3:00 PM) |
*Source: *
## Financial Requirements
| Parameter | Amount |
|———–|——–|
| **Earnest Money Deposit (EMD)** | ₹1.5 Crore (₹15 million) |
| **Tender Document Cost** | ₹10,000 (inclusive of GST) |
| **Minimum Average Annual Turnover** | ₹29 Crore (last 3 financial years) |
| **Minimum Cash-Flow Requirement** | ₹15 Crore |
*Source: *
## Technical Eligibility Criteria
Bidders must meet **any one** of the following experience requirements from the last 15 years :
| Option | Solar Capacity | BESS Capacity | Minimum Contract Value |
|——–|—————|—————|————————|
| **Option 1** | 2.7 MW | 2.19 MWh | ₹17 Crore |
| **Option 2** | 1.8 MW (2 projects) | 1.26 MWh each | ₹12 Crore each |
| **Option 3** | 0.9 MW (3 projects) | 0.63 MWh each | ₹6 Crore each |
### O&M Experience Requirement (Last 10 Years):
– At least **1 year** O&M on a solar project of minimum **2.25 MW**
– At least **6 months** O&M on a battery storage project of minimum **1.57 MWh**
## Scope of Work
The selected bidder will be responsible for :
– **Land development** – Identification and preparation of project land
– **Design & Engineering** – Complete system design for solar + BESS integration
– **Supply & Procurement** – All solar modules, BESS components, inverters, mounting structures, cables
– **Civil & Electrical Works** – Complete installation and erection
– **Testing & Commissioning** – Grid integration and performance validation
– **Permits & Licenses** – All statutory approvals and insurance
– **Operation & Maintenance** – Comprehensive O&M for **15 years**
## Project Configuration
– **Solar Capacity:** 9 MW (AC)
– **Battery Storage:** 3.15 MW power / 6.3 MWh energy capacity
– **Project Type:** Solar + Storage Hybrid
– **Application:** Grid support, peak management, improved dispatchability, and grid stability
## Business Implications
### Strategic Significance
This tender represents Himachal Pradesh’s commitment to integrating renewable energy with storage solutions to enhance grid stability. The state aims to meet over 90% of its annual energy consumption (~13,000 million units) through renewable sources .
—-