In the Matter of Approval the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations under System Strengthening Scheme in Northern Region–XXXVII (NRSS-XXXVII) – EQ
Summary:
—
**Key Dates & Delays**
– **Asset-1:** SCOD – 19.12.2019, COD – 4.12.2022 → **Time overrun: 1081 days**
– **Asset-2:** COD claimed as 5.1.2023 → Delay due to unready downstream asset by PTCUL.
– **Asset-3:** COD claimed as 5.1.2023 → Delay due to washed-out bridge preventing reactor relocation.
**PGCIL’s Claims**
– **Asset-2:** COD claimed under **Regulation 5(2)** due to downstream unreadiness.
– **Asset-3:** COD claimed under **Regulations 76 & 77** (Power to Relax & Remove Difficulty) due to force majeure-like event (bridge washout). Asset scope revised post-NRPC agreement.
**Interim Tariff Decision**
– **Asset-1:** **Interim tariff granted** at **70% of claimed AFC** for FY 2022-23 & 2023-24.
– Allowed charges:
– 2022-23 (pro rata 118 days): ₹1,284.969 lakh
– 2023-24: ₹4,172.36 lakh
– **Asset-2 & Asset-3:** **No interim tariff granted**. To be examined in final tariff order.
– Interim tariff is subject to **adjustment** per Regulation 10 of the 2019 Tariff Regulations.
**Regulatory Basis**
– Regulation 10(3) allows interim tariff for new projects if petition is adequate.
– Tariff differences will be settled later with interest (bank rate).
– Billing & collection to follow **2020 Sharing Regulations**.
**Next Steps**
– Final tariff order to be issued after detailed analysis.
– Issues of COD for Asset-2 and Asset-3 to be resolved in final order.
– Adjustments may be made based on actual vs. projected capital expenditure.
**Signatories**
– Chairperson: Shri Jishnu Barua
– Members: Shri Ramesh Babu V., Shri Harish Dudani, Shri Ravinder Singh Dhillon
—
For more information please see below link:
Related posts:
- In the matter of Approval the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for determination of transmission tariff from COD under TSA with Mundra Ultra Mega Power Project – EQ
- Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for the Northern Region ISTS and State Utility Communication Network – EQ
- Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for the Northern Region ISTS and State Utility Communication Network – EQ
- Petition for determination of transmission tariff from the COD to System Strengthening Scheme in the Northern Region–XXXVII (NRSS-XXXVII) – EQ