  3. MES issue Tender for Provn of Solar Supply at Sncos Mess Complex under GE (AF) No 2 at AF Station Jodhpur – EQ
MES issue Tender for Provn of Solar Supply at Sncos Mess Complex under GE (AF) No 2 at AF Station Jodhpur – EQ

MES issue Tender for Provn of Solar Supply at Sncos Mess Complex under GE (AF) No 2 at AF Station Jodhpur – EQ

0
0

Summary:

—-

### Eligibility Criteria:

#### A) For MES Enlisted Contractors:
– Enlisted with MES in **Class ‘D’ and above**
– Must have **MoU with Solar Power firms** having rating 1A/1B/1C/2A/2B/2C from CRISIL/CARE/FITCH/ICRA/SMERA/Brick Work Ratings
– No adverse remarks in Work Load Return (WLR)
– Experience: Successfully completed & commissioned Solar Power Plants in Government Dept/PSU in last 7 years:
– One work of capacity ≥ 32 KW **OR**
– Two works of capacity ≥ 20 KW **OR**
– Three works of capacity ≥ 16 KW

#### B) For Non-MES Enlisted Contractors:
– Must meet D Class enlistment criteria per MES Manual of Contracts 2020 (Para 1.4 & 1.5) including:
– Satisfactory completion of requisite value works with Central/State Govt/PSUs
– Annual turnover, bank solvency, working capital
– Same solar MoU/experience requirements as above
– Not suspended/debarred/blacklisted by any Govt Dept/PSU/Autonomous Body
– If already executing MES works, total value ≤ twice the tendering limit of eligible class
– Unenlisted contractors securing **two MES works** must get enlisted with MES, else ineligible for future tenders

### Key Bid Process Rules:
– **Two-cover system:** Cover-1 (Technical Bid) + Cover-2 (Financial Bid)
– Scanned DD for tender cost & EMD (as applicable) to be uploaded in Cover-1
– Physical copies of DD/EMD must reach Accepting Officer within **7 days of bid submission end date**, else:
– Enlisted contractors: Financial bid opened but may be banned for 6 months
– Unenlisted contractors: Financial bid **not opened**, name circulated for 6-month debar

### Performance Security Deposit:
– **5% of contract sum** to be deposited within 28 days of acceptance of tender
– Failure = cancellation of award + forfeiture of EMD

### Important Conditions for Businesses:
| Condition | Implication |
|———–|————–|
| No subletting | Work cannot be subcontracted to third parties; only sons/daughters/spouse/own employees can execute via PoA |
| Related firms not allowed | If proprietors/partners/directors are common, only one firm can bid; AO’s decision final |
| No rate revision after bid opening | Upward revision or voluntary reduction = willful default; EMD forfeited + defaulting firm banned from re-tender |
| BOQ revision | If BOQ revised, quoting on old BOQ = non-bonafide; such bids rejected |
| Deficiency rectification | 7 days given to rectify document deficiencies in Cover-1, else financial bid not opened |
| Right to reject | Accepting Officer can reject any bid (including lowest) without assigning reason |
| Jurisdiction | Courts at the place of tender issuance (Jodhpur) have exclusive jurisdiction |
| EPF compliance | Contractor must produce PF Code No. before commencement of work |

### Additional Notes:
– If less than 7 eligible bidders after Cover-1 opening, contractors **one class below** (or two classes below for remote areas) may be considered subject to work-in-hand limits and upgradation criteria.
– Foreign firms not eligible. Indian firms with foreign nationals as directors require security clearance.
– Tenderers are deemed to have full knowledge of site conditions, drawings, and specifications – site visit advised.

## 💼 Business Points – Key Takeaways

| Business Aspect | Action/Implication |
|—————-|——————–|
| **Solar experience mandatory** | Must have completed solar power plants (Govt/PSU) of specified capacities – no exceptions. |
| **Solar rating/MoU required** | Either contractor must have CRISIL/CARE etc. solar rating, or have MoU with a rated solar firm. |
| **EMD & tender cost** | ₹76,000 EMD + ₹500 tender cost via DD – physical copies must reach within 7 days post-bid closure. |
| **No subletting** | Work must be done by firm’s own resources or specified close relations – no outsourcing. |
| **Performance security** | 5% of contract sum within 28 days of acceptance – plan cash flow accordingly. |
| **Penalty for rate changes post-bid** | Do not revise rates after opening – leads to forfeiture + ban from re-tender. |
| **Unenlisted contractors** | Must meet D Class financial & work experience criteria; after 2 MES works, must get enlisted. |
| **Related firms** | If common ownership exists, only one firm can bid – AO decides which. |
| **Jurisdiction** | Any dispute will be heard in Jodhpur courts only. |
| **Right to reject** | AO can reject any bid without reason – no compensation. |

For more information please see below link: