1. Home
  2. Policy & Regulation
  3. Petition of the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations of TPSL – EQ
Petition of the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations of TPSL – EQ

Petition of the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations of TPSL – EQ

0
0

Summary:

### Key Business & Legal Details

| **Aspect** | **Details** |
| :— | :— |
| **Petitioner** | T.P. Saurya Limited (TPSL) – a renewable power generator. |
| **Respondents** | Powergrid Corporation of India Limited (PGCIL) & CTUIL, among others. |
| **Legal Basis** | Section 79(1)(c) & (f), Section 38(2)(b)&(c) of the Electricity Act, 2003; Regulation 13(8) of the CERC Sharing of Inter-State Transmission Charges and Losses Regulations, 2020. |
| **Relief Sought** | (i) Direction to PGCIL to pay applicable **Yearly Transmission Charges (YTC)** as per Regulation 13(8); and/or (ii) Compensation from PGCIL/CTUIL for generation loss and financial loss due to transmission system not being ready until **December 12, 2025**. |
| **Date of Hearing** | April 17, 2026. |
| **Next Hearing Date** | **July 9, 2026**. |

### Current Status & Timeline

| **Event** | **Deadline** |
| :— | :— |
| Respondents (PGCIL, CTUIL, others) to file replies | Within 6 weeks of April 17, 2026 (approx. **May 29, 2026**) |
| TPSL to file rejoinder(s) | Within 5 weeks after receiving replies |
| CTUIL to submit project-specific details (table data) | Along with its reply (by ~May 29, 2026) |
| Next hearing | **July 9, 2026** |

### Critical Business Implications

1. **Transmission Delay Risk Allocation**: This petition tests whether generators can recover lost revenue when transmission infrastructure (built by PGCIL/CTUIL) is delayed. A favorable ruling for TPSL would set a significant precedent requiring transmission utilities to compensate generators for evacuation constraints.

2. **Regulation 13(8) – Yearly Transmission Charges (YTC)**: Under the 2020 Sharing Regulations, generators may be entitled to certain transmission charge adjustments when systems are not ready. TPSL is specifically seeking applicable YTC payments from PGCIL.

3. **Financial Exposure for PGCIL/CTUIL**: If TPSL succeeds, PGCIL and CTUIL could face material claims from multiple generators whose projects were delayed by transmission under-readiness. This may prompt a reassessment of transmission project planning and execution accountability.

4. **Generation Loss Quantification**: TPSL must prove:
– The date its project was ready to inject power.
– The quantum of power it could have generated.
– The financial value of lost generation (likely based on PPA tariff or market price).

5. **Project Viability Impact**: For TPSL, any delay in compensation affects project cash flows, debt servicing, and return on equity. The longer the litigation, the greater the financial strain.

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network