Summary: — ### **1. Case Details** – **Petition No.**: 80/TT/2025 – **Subject**: Determination of **Transmission Tariff** for assets under the **Transmission System Strengthening Scheme for evacuation of power from Solar Energy Zones in Rajasthan (8.1 GW) under Phase-II-Part B1**. – **Petitioner**: **Power Grid Corporation of India Limited (PGCIL)** – **Respondents**: **Ajmer Vidyut Vitran Nigam Limited […]
Summary: —- **BACKGROUND:** – **Remand Order:** Appellate Tribunal for Electricity (APTEL) remanded back CERC’s earlier order dated 29.6.2018. – **Reason for Remand:** APTEL directed re-determination of tariff based on: 1. Actual capital cost 2. Legitimate weighted average interest on loan (WAROI) 3. Grossed-up return on equity based on true effective tax rates 4. Correct useful […]
Summary: —- **KEY POINTS OF PROCEEDINGS:** 1. **Interim Application (IA 97/2025) – Allowed** • Petitioner’s application for amendment of prayers in Petition granted. • Amended petition taken on record; IA disposed of. 2. **Directions to Respondents** • Respondents granted **final opportunity** to file replies within **7 days** (copy to Petitioner). • Petitioner may file rejoinder […]
Summary: — ### **1. Background** * The petition is before the **Central Electricity Regulatory Commission (CERC)** and pertains to **truing-up of transmission tariff for the 2014–19 period** and **determination of tariff for the 2019–24 period**. * The assets involved are **two 765 kV line bays at the 765/400 kV Raipur Pooling Station (Powergrid)** associated with […]
Summary: — ### **1. Background** * The matter relates to a petition filed before the **Central Electricity Regulatory Commission (CERC)** by **Delhi Transco Limited (DTL)**. * The petition seeks **truing-up of transmission tariff for the 2019–24 control period** and **determination of tariff for the 2024–29 period**. * The assets involved are: * **400 kV Bawana […]
Summary: — ### **1. Introduction & Case Overview** – **Petitioner:** Power Grid Corporation of India Limited (PGCIL) – **Subject:** Petition for truing up of transmission tariff for the period **2019–24** and determination of transmission tariff for the period **2024–29** for **Combined Assets** under the “System Strengthening–XX” scheme in the Southern Region. – **Legal Basis:** Electricity […]
Summary: — ### **1. Regulatory Outcome** * CERC has **approved truing-up of transmission tariff for FY 2019-24** and **determined tariff for FY 2024-29**. * Applicable to **Combined Asset under URI-II HEP Transmission System** in the **Northern Region**. * Order dated **5 December 2025**. — ### **2. Project & Asset Overview** * **Asset Owner:** Power Grid […]
Summary: — **Subject of the Petition** North East Transmission Company Limited (NETC) has filed a petition seeking: 1. **Truing up** of the transmission tariff for the tariff period **2019–24**. 2. **Determination** of the transmission tariff for the tariff period **2024–29** for assets under the **400 kV Palatana–Bongaigaon Transmission System Project** in the North Eastern Region. […]