## **Case Overview**

* **Petition No.:** 372/TT/2024
* **Filed By:** Power Grid Corporation of India Limited (PGCIL)
* **Respondents:** Tamil Nadu Generation and Distribution Corporation Ltd. (TANGEDCO) and others
* **Subject:** Determination of transmission tariff from COD up to 31.03.2029 for:

1. Implementation of 220 kV bus sectionalizer with bus coupler & transfer bus coupler at Pavagada Power Station.
2. Additional 220 kV bus bar extension works to integrate Renewable Energy (RE) generation projects at Pavagada (Tumkur) PS.

* These are part of the larger project: *“Augmentation of transformation capacity by 1×500 MVA, 400/220 kV ICT (6th) and common facility works at Pavagada (Tumkur) PS”* in the Southern Region.

## **Hearing Details**

* **Date of Hearing:** 16 September 2025
* **Coram:**

* Shri Jishnu Barua (Chairperson)
* Shri Ramesh Babu V. (Member)
* Shri Harish Dudani (Member)
* Shri Ravinder Singh Dhillon (Member)
* **Next Listing:** 21 October 2025

## **Key Submissions & Directions**

* **Petitioner’s Submission:**

* Requested determination of tariff for the said assets from COD till 31.03.2029.

* **Commission’s Directions:**
PGCIL must submit an affidavit (within two weeks) addressing:

1. **Justification** for claiming the ICT (Interconnecting Transformer) separately without commissioning Parts 2 and 3 of the works.
2. **Timeline Clarification:** As per CTUIL addendum, Parts 1 and 2 were due in **December 2023**, but the petition claims a revised SCOD (Scheduled COD) of **7 February 2024**. PGCIL must justify this delay.

* **Respondents’ Role:**

* Respondents to file their replies within **one week**.
* PGCIL may file rejoinders, if any, within **one week thereafter**.

## **Order**

* The matter stands adjourned to **21 October 2025** for further hearing.
* Order signed by **T. D. Pant, Joint Chief (Law), CERC**.