Petition for the determination of transmission tariff for “Strengthening of OPGW network within the Eastern Region Grid and Connectivity with other regions” in the Eastern Region – EQ
Summary:
—-
### Key Procedural Developments
#### 1. **Status of Pleadings**
– The representatives of PGCIL submitted that the **pleadings have been completed**. They requested the Commission to consider their submissions and allow the transmission tariff for the upcoming period.
#### 2. **Respondent Non-Appearance**
– **None of the respondents (including BSPHCL and five others) appeared** during the virtual hearing, despite having received notice. This indicates a lack of active opposition or contest at this stage, though they retain the right to file written replies.
### Commission’s Directives
Despite the respondents’ absence, the Commission issued the following orders:
– **Opportunity for Respondents:** The respondents were directed to file their replies (if any) within **two weeks**. PGCIL may file a rejoinder within one week thereafter. This ensures the respondents are not shut out from the process.
– **Additional Information Required:** The Commission directed PGCIL to furnish the following specific information on affidavit within one week:
– **Revised Cost Estimate (RCE-II) with respect to Asset-II.** This suggests the Commission needs updated cost justification for one of the four assets under the project.
### Business Implications and Conclusion
– **For PGCIL (Petitioner):** While the pleadings are complete, the Commission has not yet approved the tariff. PGCIL must now quickly provide the RCE-II details for Asset-II to avoid delays. The lack of respondent opposition is favorable but does not guarantee automatic approval.
– **For Respondents (BSPHCL, etc.):** They have been given a final two-week window to file replies. If they fail to do so, the Commission may proceed with the tariff determination based solely on PGCIL’s submissions.
– **For the Industry:** This case highlights CERC’s thoroughness in requiring detailed cost estimates (like RCE-II) even when a petition appears unopposed. The final order will set the transmission charges for this crucial OPGW network strengthening project in the Eastern Region, impacting grid connectivity and reliability.
—-
For more information please see below link: