  3. Petition for Truing up and determination of tariff for “System Strengthening Scheme in South-Western Part of Northern Grid (Part-B)” in the Northern Region – EQ
Petition for Truing up and determination of tariff for “System Strengthening Scheme in South-Western Part of Northern Grid (Part-B)” in the Northern Region – EQ

Petition for Truing up and determination of tariff for “System Strengthening Scheme in South-Western Part of Northern Grid (Part-B)” in the Northern Region – EQ

0
0

Summary:

## 📌 Case Details

* **Authority:** Central Electricity Regulatory Commission (CERC), New Delhi
* **Petition No.:** 219/TT/2025
* **Petitioner:** Power Grid Corporation of India Limited (PGCIL)
* **Respondents:** Uttar Pradesh Power Corporation Ltd. & 17 others
* **Date of Hearing:** 16 September 2025
* **Coram:** Shri Jishnu Barua (Chairperson), Shri Ramesh Babu V., Shri Harish Dudani, Shri Ravinder Singh Dhillon

## 📝 Subject

* Petition for **truing up of tariff (2019–24)** and **determination of tariff (2024–29)** for the **400 kV S/C Kankroli–Jodhpur Transmission Line** with associated bays.
* This project falls under the **“System Strengthening Scheme in South-Western Part of Northern Grid (Part-B)”**.

## ⚖️ Proceedings

* **PGCIL submission:**

* Petition amended as per CERC’s direction.
* **Re-conductoring works (including bay modifications)** carried out.
* Capital cost incurred on re-conductoring claimed as **additional capitalization** under the same project.

* **Respondents (BRPL & BYPL):**

* Sought time to file replies.

* **Commission’s direction:**

* All parties, including BRPL & BYPL, to file **written submissions within 2 weeks** (advance copy to be served).
* **Order reserved** subject to submissions.

## 📅 Current Status

* No final decision yet.
* Commission has **reserved orders** after receiving submissions.

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network