Petition of the PPA and GUVNL for supply of 200 MW Solar Power plant in the State of Gujarat for Force Majeure events – EQ

Petition of the PPA and GUVNL for supply of 200 MW Solar Power plant in the State of Gujarat for Force Majeure events – EQ

0
0

Summary:

# GERC — Petition No. 2460/2025 (Martial Solren Pvt. Ltd. v. GUVNL) — Daily Order dated 19-Aug-2025

* **Relief sought:** Extension of **SCOD** for a **200 MW solar PV** project under the **PPA dated 15-Dec-2022**, invoking **Force Majeure**. Also includes **IA 24/2025** and **IA 67/2025** under **Sec. 94(2)** for urgent directions. 
* **Coram & date:** Members **Mehul M. Gandhi** and **S. R. Pandey**; **19/08/2025**. Parties represented by **Ms. Nipun Sharma** for Petitioner and **Mr. Aneesh Bajaj** (with **Mr. K. T. Shah**) for Respondent. 
* **Project status:** Petitioner states the **remaining 50 MW was commissioned on 26-Jul-2025**; the **limited issue** is now **LDs in light of FM**. Petitioner has received payments but seeks **clarity on LD deductions**. 
* **Respondent’s position:** No objection to adjournment; says **payments were made after reducing LDs**. Parties agree to **reconciliation of deductions**. 

## Directions

1. **Petitioner’s further submissions:** **within 1 week** (copy to Respondent). 
2. **Respondent’s reply:** **within 1 week** (copy to Petitioner). 
3. **Petitioner’s rejoinder (if any):** **within 1 week** thereafter. 
4. **Complete pleadings:** **within 3 weeks** (overall). **Order accordingly.** 

### Handy timeline (counting from 19-Aug-2025)

* Submissions & Reply: by **26-Aug-2025**.
* Rejoinder: about **02-Sep-2025**.
* All pleadings complete: by **09-Sep-2025**. 

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network