IISRB issue Tender for EPC Contract for DEPSCC on Turnkey basis and Comprehensive O&M for 1O Yrs of 2.4 MW DC, 2 MW AC Grid Connected Solar PV Power Plant at IISER Bhopal – EQ
Summary:
—
### **1. PROJECT OVERVIEW**
– **Project:** EPC contract for design, engineering, procurement, supply, construction, commissioning, and 10-year comprehensive O&M of a 2.4 MW DC / 2 MW AC grid-connected solar power plant at IISER Bhopal.
– **Scope:** Turnkey basis, including civil, electrical, structural, SCADA, evacuation to 33 kV substation, and 10-year O&M.
– **Location:** IISER Bhopal Campus, Bhauri, Bhopal, Madhya Pradesh.
– **NIT No.:** IWD/SE/NIT/2025-26/47 dated 01/02/2025.
– **EOI Reference:** IWD/SE/EOI/2025-26/182 dated 21/07/2025.
—
### **2. KEY DATES & FINANCIALS**
– **Bid Submission Deadline:** 29/12/2025, 3:00 PM (online).
– **Hard Copy of Technical Bid:** 30/12/2025, 3:00 PM.
– **EMD & Technical Bid Opening:** 30/12/2025, 3:30 PM.
– **Price Bid Opening:** To be communicated later.
– **Earnest Money Deposit (EMD):** ₹24,00,000/-
– 50% or ₹20 lakh (whichever less) via bank transfer, balance via bank guarantee.
– **Performance Guarantee:** 5% of contract value.
– **PV Module Performance BG:** 5% of PV module cost (taken as 25% of contract value), valid 25 years.
– **O&M Bank Guarantee:** 5% of O&M contract price, valid 10 years.
– **Security Deposit:** 2.5% of tendered value, deducted from bills.
—
### **3. CONTRACT DURATION**
– **Original Work:** 5 months.
– **Defect Liability Period (DLP):** 1 year after commissioning.
– **Comprehensive O&M:** 10 years after DLP.
—
### **4. TECHNICAL SPECIFICATIONS HIGHLIGHTS**
– **PV Modules:** N-type Topcon-DCR bifacial, ≥550 Wp, ≥22% efficiency, 25-year warranty.
– **Inverters:** 250 kW string inverters, 1500 V DC, 99.02% max efficiency.
– **Transformer:** 2200 kVA, oil-immersed, ONAN cooling.
– **Mounting Structure:** Hot-dip galvanized, seasonal tilt, designed for 180 km/h wind.
– **SCADA & Monitoring:** Cloud-based, string-level monitoring, weather station, remote access.
– **Evacuation:** 33 kV underground cable to IISER substation.
– **Civil Works:** Control room, fencing, roads, drainage, cable trenches, foundation.
—
### **5. PAYMENT SCHEDULE**
| **Stage** | **% of Contract Price** |
|———–|————————–|
| Supply of equipment & materials | 50% |
| Civil work completion | 10% |
| Erection, commissioning, acceptance | 10% |
| 10-year O&M | 30% (escalating yearly) |
| **Total** | **100%** |
—
### **6. PERFORMANCE GUARANTEES**
– **Annual Generation Guarantee (NEEGG):** 36 lakh kWh/year with 0.7% annual degradation.
– **Performance Ratio (PR):** ≥80% at commissioning.
– **Compensation for Shortfall:** As per MPERC tariff rates.
– **Plant Uptime:** Fault rectification within 24 hours.
—
### **7. KEY CONTRACTUAL CONDITIONS**
– **Taxes:** All taxes (GST, labour cess, etc.) included in bid price.
– **Statutory Approvals:** Contractor’s responsibility (DISCOM, CEIG, MPERC, etc.).
– **Site Inspection:** Mandatory; no claim for ignorance of site conditions.
– **Labour & Safety:** Compliance with CPWD Safety Code, labour laws, ESI, EPF.
– **Insurances:** Contractor to insure works during construction and O&M.
– **Dispute Resolution:** Three-tier internal mechanism, then courts in Bhopal.
– **Governing Documents:** CPWD GCC-EPC 2024 with latest corrections.
—
### **8. OBLIGATIONS DURING O&M (10 YEARS)**
– Daily operation, monitoring, reporting.
– Preventive & corrective maintenance.
– Module cleaning twice monthly.
– Spare parts management.
– Compliance with scheduling & forecasting (MPERC).
– Security, housekeeping, civil upkeep.
– Annual generation reporting and shortfall compensation.
—
### **9. MANDATORY SPARES**
– PV modules, inverters, cables, relays, fuses, SCADA components, etc., to be maintained on-site and handed over after O&M.
—