Petition for Adoption of tariff for 420 MW RTC power from ISTS-connected Renewable Energy Power Projects (SECI-RTC-IV) by the Ministry of Power, Government of India – EQ
Summary:
# CERC — RoP in Petition No. 722/AT/2025
* **Matter:** Adoption of tariff under **Section 63** for **420 MW RTC** power from **ISTS-connected RE projects (SECI-RTC-IV)**, discovered via competitive bidding per **MoP guidelines dated 9-Jun-2023 (with amendments)**. 
* **Petitioner:** **Solar Energy Corporation of India Ltd. (SECI)**; **Respondents:** Hero Solar Energy Pvt. Ltd. & Ors. 
* **Hearing held:** **28-Aug-2025**; **Coram:** Shri Jishnu Barua (Chairperson), Shri Ramesh Babu V., Shri Harish Dudani, Shri Ravinder Singh Dhillon (Members). 
* **Parties present (for SECI):** Shri Rahul Ranjan (Adv.), Shri Kumar Suryamauli (Adv.); Hexa Climate: Shri Rohit Ahuja. 
## Orders passed
1. **Petition admitted; notice issued** to Respondents. 
2. **Respondents’ replies** within **two weeks**; **SECI rejoinder** within **one week thereafter**. 
3. **SECI to file an affidavit within one week** certifying that the **discovered tariff rates are reasonable**. 
4. **Next hearing/listing:** **25-Sep-2025**. (That’s tomorrow in Asia/Kolkata.) 
—-
For more information please see below link:
Related posts:
- Petition for the Adoption of Tariff of 760 MW Firm and Dispatchable Power (APPS) from ISTS Connected Renewable Energy Power Projects with Energy Storage Systems, Ministry of Power, Government of India – EQ
- Petition for Adoption of Tariff for procurement of power from the 760 MW Firm and Dispatchable Power (Assured Peak Power Supply) from ISTS-Connected Renewable Energy Power Projects – EQ
- Petition of the CERC (Conduct of Business) Regulations of RE Power Developers for Supply of 1500 MW Firm and Dispatchable Power from ISTS-Connected Renewable Energy Power Projects – EQ
- Petition for Adoption of tariff for the ISTS Grid connected Solar Power Projects of 1200 MW with Energy Storage System by Ministry of Power, Government of India – EQ