Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ
Summary:
—-
Document 1: CERC Hearing Proceedings (875/TT/2025)
Key Proceedings:
Petitioner’s Submission: PGCIL filed for tariff determination for the 2024-29 period.
MSEDCL’s Request: Respondent No. 2 (MSEDCL) sought 4 weeks to file a reply.
Commission’s Directions:
PGCIL to implead CTUIL as a party and file a revised memo within a week.
Issue notice to all respondents.
Respondents to file replies within 4 weeks; PGCIL may file rejoinder within 2 weeks thereafter.
Specific Information Sought:
From CTUIL (within 2 weeks):
Status of 220 kV downstream transmission system under GETCO.
Whether Asset-2’s deemed COD can be considered without commissioning the 765 kV Navsari–Padghe line and related ICT bays.
From PGCIL (within 2 weeks):
Justification for claiming COD of Asset-2 (20.3.2025) without associated infrastructure.
Clarify discrepancies in transmission line nomenclature and lengths as per IA (6.7.2022) vs. CTUIL’s OM (13.1.2022).
Map all assets according to IA vs. CTUIL OM.
Confirm commissioning status and CODs of Navsari (New) substation elements.
Justify capital cost vs. awarded cost (LoA).
Provide Form-5 for Asset-2, compensation payment proofs, cost apportionment details for shared multi-circuit towers, liability flow statement, notional IDC calculations, Form-9C, and cash IDC statement.
Next Hearing: Listed for 15 January 2026.
—-
For more information please see below link:
Related posts:
- Petition for Truing Up and determination of transmission tariff for the Itarsi- Dhule Transmission Line at Khandwa” in the Western Region – EQ
- Petition for determination of the transmission tariff from COD of state-of-the-art UNMS for the Northern Region ISTS and State Utility Communication Network – EQ
- Petition for Truing up and determination of transmission tariff under Western Region System Strengthening Scheme (XVIII) in the Western Region – EQ
- Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff for “Eastern Region Strengthening Scheme-VII (ERSS-VII)” – EQ


