Summary:

—-

Document 1: CERC Hearing Proceedings (875/TT/2025)

Key Proceedings:

Petitioner’s Submission: PGCIL filed for tariff determination for the 2024-29 period.

MSEDCL’s Request: Respondent No. 2 (MSEDCL) sought 4 weeks to file a reply.

Commission’s Directions:

PGCIL to implead CTUIL as a party and file a revised memo within a week.

Issue notice to all respondents.

Respondents to file replies within 4 weeks; PGCIL may file rejoinder within 2 weeks thereafter.

Specific Information Sought:

From CTUIL (within 2 weeks):

Status of 220 kV downstream transmission system under GETCO.

Whether Asset-2’s deemed COD can be considered without commissioning the 765 kV Navsari–Padghe line and related ICT bays.

From PGCIL (within 2 weeks):

Justification for claiming COD of Asset-2 (20.3.2025) without associated infrastructure.

Clarify discrepancies in transmission line nomenclature and lengths as per IA (6.7.2022) vs. CTUIL’s OM (13.1.2022).

Map all assets according to IA vs. CTUIL OM.

Confirm commissioning status and CODs of Navsari (New) substation elements.

Justify capital cost vs. awarded cost (LoA).

Provide Form-5 for Asset-2, compensation payment proofs, cost apportionment details for shared multi-circuit towers, liability flow statement, notional IDC calculations, Form-9C, and cash IDC statement.

Next Hearing: Listed for 15 January 2026.

—-