### **1. SUBJECT OF THE PETITIONS**

| Petition No. | Purpose / Relief Sought |
|————–|————————–|
| **824/TL/2025** | Application related to the **grant of Transmission License** to Angul Sundargarh Transmission Limited (ASTL), including any clarifications or replacements. |
| **825/AT/2025** | Application under **Section 63 of the Electricity Act, 2003** for **adoption of tariff** discovered through competitive bidding for ASTL as a Transmission Service Provider for inter-state transmission systems. |

### **2. STATUS OF COMPLIANCE (AS OF HEARING)**

* **Petitioner (ASTL)** has complied with the Commission’s earlier direction (Record of Proceedings dated **3 December 2025**) by:
* Filing an **amended memo of parties**.
* **Impleading all beneficiaries** of the **2400 MW Talabira Thermal Power Plant** and **WBSEDCL** as parties to the petitions.
* **Respondent (CTUIL)** has filed a **compliance affidavit** dated **9 December 2025** as per directions in the RoP dated **13 November 2025**.

### **3. PROCEEDINGS & OUTCOME**

* The learned counsel for ASTL presented the above compliance updates before the Commission.
* After hearing the submissions, the **Commission reserved the matter for orders**.
* No further arguments or objections were recorded from other parties at this hearing.

### **4. NEXT STEPS**

* The Commission will issue its **final order** in due course based on the compliance records and submissions.
* The order will likely address:
* The grant of transmission license (Petition 824).
* Adoption of the competitively bid tariff (Petition 825).