  3. Petition for Truing up and for the determination of transmission tariff for Uravakonda-Veltoor, Kamavarapukota-Suryapet I & II lines for tariff period – EQ
Petition for Truing up and for the determination of transmission tariff for Uravakonda-Veltoor, Kamavarapukota-Suryapet I & II lines for tariff period – EQ

Petition for Truing up and for the determination of transmission tariff for Uravakonda-Veltoor, Kamavarapukota-Suryapet I & II lines for tariff period – EQ

0
0

Summary:

—-

**Key Entities:**

– **Petitioner:** APTRANSCO (Transmission Corporation of Andhra Pradesh Limited)
– **Respondents:** Transmission Corporation of Telangana Limited (TSTRANSCO) and another (likely CTUIL – Central Transmission Utility of India Ltd.)
– **CTUIL** was present at the hearing as Respondent No. 2.

**Date of Hearing:** 20 November 2025

**Proceedings Summary:**

1. The petitioner’s counsel stated that **pleadings are complete** and requested that the tariff be allowed as prayed in the petition.
2. **No representative appeared for the primary respondent (Telangana Transmission Company)**, except CTUIL.
3. After hearing the submissions, the **CERC reserved the matter for order** (decision pending).

**Business Implications:**

– This is a **tariff approval proceeding** before CERC, impacting **inter-state transmission charges**.
– The lines in question (Uravakonda–Veltoor and Kamavarapukota–Suryapet) are critical **inter-regional transmission corridors** connecting Andhra Pradesh and Telangana.
– The truing up for 2014–2019 involves **cost reconciliation and revenue adjustment** for past operations.
– The tariff determination for 2019–2024 will affect **APTRANSCO’s revenue recovery, cost pass-through to beneficiaries, and future transmission pricing** in the region.
– The absence of Telangana’s representation may indicate either **no objection** or reliance on CERC’s regulatory process.