1. Home
  2. Policy & Regulation
  3. Petition for Adoption of the Tariff and approval of PPA for the procurement of 7 MW for meeting its Renewable Purchase Obligation – EQ
Petition for Adoption of the Tariff and approval of PPA for the procurement of 7 MW for meeting its Renewable Purchase Obligation – EQ

Petition for Adoption of the Tariff and approval of PPA for the procurement of 7 MW for meeting its Renewable Purchase Obligation – EQ

0
0

Summary:

## Case Background

* **Petitioner**: *Nidar Utilities Panvel LLP (NUPLLP)* – deemed distribution licensee for Panvel SEZ.
* **Respondent**: *PTC India Limited*.
* **Relief sought**: Adoption of tariff and approval of a **short-term Power Purchase Agreement (PPA)** for **7 MW round-the-clock (RTC) renewable energy** for **1 year (Sep 2025 – Aug 2026)**.

## Key Facts

* NUPLLP projected demand rising to **~18 MW** by Aug 2025.
* Issued RfP (21 May 2025) for 7 MW RTC renewable power at **Maharashtra STU periphery**.
* **Bids received (June 2025)**:

* **PTC India Ltd (Greta Energy – biomass)** at ₹5.80/kWh
* **Vayunandana Power Ltd (biomass)** at ₹6.42/kWh.
* After e-RA, PTC remained lowest (L1) at ₹5.80/kWh.
* **Letter of Award issued**: 1 July 2025; **PPA signed**: 9 July 2025.

## Commission’s Observations

* Tariff of **₹5.80/kWh** compares favorably with:

* Previous NUPLLP PPAs (e.g., ₹6.60/kWh in Dec 2024 with Vayunandana).
* Generic biomass tariff (₹6.87/kWh for FY 2025–26).
* Market-discovered tariffs on DEEP portal (ranging ₹5.35–7.90/kWh across states/utilities).
* Biomass RTC supply aligns well with NUPLLP’s **load curve** and helps **fulfill Renewable Purchase Obligation (RPO)** targets.
* Commission recognized risks of relying on exchanges due to **transmission losses (65–80 paise/unit)** and **DSM penalties**.

## Final Order

1. **Petition allowed**; IA disposed.
2. **Tariff of ₹5.80/kWh adopted** (at Maharashtra STU periphery).
3. **PPA between NUPLLP & PTC approved** for 7 MW RTC renewable energy from **1 Sep 2025 – 31 Aug 2026**.
4. NUPLLP permitted to procure additional short-term power via bidding or exchanges if demand exceeds contracted quantum.

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network