1. Home
  2. Policy & Regulation
  3. Petition of the GERC (Conduct of Business) Regulations for construction of the evacuation infrastructure and quashing of the letter – EQ
Petition of the GERC (Conduct of Business) Regulations for construction of the evacuation infrastructure and quashing of the letter – EQ

Petition of the GERC (Conduct of Business) Regulations for construction of the evacuation infrastructure and quashing of the letter – EQ

0
0

Summary:

## Case Background

* **Petitioner**: *Kintech Solarbikaner Pvt. Ltd.* – developer of a **50 MW Wind-Solar Hybrid captive project**.
* **Respondent**: *Gujarat Energy Transmission Corporation (GETCO)*.
* **Main Petition (No. 2535/2025)**: Sought **extension of time** for completion of evacuation infrastructure at **220 kV Rajula Substation** and quashing of GETCO’s warning letter (07.07.2025).
* **Interim Application (IA No. 79/2025)**: Requested urgent listing, interim stay on revocation of connectivity, and protection against encashment of Bank Guarantee.

## Petitioner’s Submissions

* Applied for **Stage I & II connectivity** in July 2024; granted on 31.08.2024.
* Paid ₹5 crore Bank Guarantee in May 2025.
* Required to complete evacuation infrastructure **within 12 months** (by 31.08.2025) per *GERC Tariff Order (22.02.2024)* and *Procedure for Grant of Connectivity, 2023*.
* Claimed delays due to **force majeure/unforeseen events**:

* 92 days lost to heavy continuous rains.
* 32 days delay in drawing approval by GETCO.
* Transformer, breaker & panel delivery delays due to market crisis.
* 78 days delay in statutory approvals (Section 68 & 164 of Electricity Act).
* Sought **365-day extension** beyond 31.08.2025 and protection against connectivity termination and BG encashment.

## Respondent’s (GETCO) Position

* Did not object to admission of the petition.
* Requested **4 weeks’ time to file reply**.

## Commission’s Interim Ruling (04.09.2025)

* Petition admitted.
* **Interim relief granted**:

* Directed GETCO **not to terminate the connectivity** until next hearing.
* Clarified **no stay on BG encashment**—that remains at GETCO’s discretion.
* Relief is **temporary** and valid only till next hearing.
* Next date of hearing to be intimated separately.

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network