  3. Petition for determination of the transmission tariff from the COD for assets under “Eastern Region Expansion Scheme – XXXVI (ERES-XXXVI)” in the Eastern Region – EQ
Petition for determination of the transmission tariff from the COD for assets under “Eastern Region Expansion Scheme – XXXVI (ERES-XXXVI)” in the Eastern Region – EQ

Petition for determination of the transmission tariff from the COD for assets under “Eastern Region Expansion Scheme – XXXVI (ERES-XXXVI)” in the Eastern Region – EQ

0
0

Summary:

**Petition-wise Details:**

| Petition No. | Project / Asset Description | Region |
|————–|——————————|——–|
| 533/TT/2025 | Eastern Region Expansion Scheme – XXXVI (ERES-XXXVI) | Eastern Region |
| 563/TT/2025 | North Eastern Region Strengthening Scheme – XIII | North Eastern Region |
| 729/TT/2025 | Communication System under Eastern Region Fibre Optic Expansion Project (Additional Requirement) | Eastern Region |
| 730/TT/2025 | (Details not fully specified, but related to transmission assets) | – |

**Key Developments:**

1. **Petitioner’s Submissions:**
– No replies filed by respondents in Petitions **563, 729, and 730/TT/2025**.
– Technical Validation Letter and replies to Record of Proceedings (RoP) filed in these matters.

2. **Commission’s Directions:**

**To Respondents (All Petitions):**
– File replies, if any, within **two weeks**, with advance copy to PGCIL.
– PGCIL may file rejoinder within **one week** thereafter.

**To Petitioner (Specific Petitions):**
– **Petition No. 730/TT/2025:** Submit **liability flow statement in Excel format** (within two weeks).
– **Petition No. 563/TT/2025:** Submit details of **interest rate considered for floating rate in IDC calculation**, along with linked Excel of IDC statement (within two weeks).

For more information please see below link: